Jared asked why the companies that already make gas turbines can't simply make more of them, given that GE's turbines are sold out for years. Blake's answer is that incumbents are rewarded for scarcity. It bears on the AI data-center power shortage and the capex debate.
Our plan was to make one gigawatt of turbines in a year. We have one prospective customer, which that one customer wants to deploy 1.6 gigawatts of turbines every 30 days. The moment this thing is proven in the field, there is firm customer demand as far as the eye can see.
So why can't the companies that already make turbines just make more of them?
There's something like one to two trillion dollars in market cap of industrial companies that were founded more than a century ago that have not had to innovate or compete in a long time. Customers are clamoring for more power. They say, great, my prices have tripled. My margins are through the roof. My stock price is up. My stock options are in the money. Why should I make a capital investment that Wall Street might punish me for? So they put their feet up and they don't do much.
Blake traces this decay in America's industrial power back to the 1970s.
1973, we banned supersonic flight. The same year, we stopped the rapid exponential increase in electricity per capita. There's this chart that goes all the way back to 1882 when Edison flipped the switch on the first electric grid. In the out years, it was about 6% annual compounded growth in…
GE's gas turbines are sold out through 2030. The biggest bottleneck is a single part, the blades inside the engine that sit in the hottest gas. To not melt, they have to be made of exotic alloys and manufactured with specialized techniques. Boom ran into this the moment it started buying parts for…