Inevitable · Climate & Energy · November 2026
Cody Simms asked whether a "flexible" data center has to give up five-nines uptime. She says no: data centers can respond to the grid with batteries, nearby generation or shifting load, and the assumption that flexibility means switching off the AI is a mistake.
…as non-firm, meaning it doesn't get its firm power every single hour of the year, of which, by the way, there are 8,760. It does not mean that the data center needs to take the hit on uptime for the balance of hours where it is drawn down. What it needs to do is find power firming somewhere else.
Just can't pull from the grid.
Yes. So non-firm to the grid, the more clear rules like the one I have written for Texas are, the more clear rules are that define what is your non-firm exposure to the grid, the more clear it is what you should do to manage that non-firmness at your site. Should you shift compute? Should you shift IT load? Should you add a battery? Should you PPA with a nearby generator who will manage a lot of the grid problems for you and reduce your exposure to non-firm power? Essentially, where we've gone in the United States, in my view, is deeply unfortunate. Our understanding of the words load flexibility and data center flexibility automatically transferred people's minds to the data center has to curtocompute.
As consumers, we've all had demand response events in our own homes.
You've had thermostats and stuff, and it's like, yeah, you need to be more uncomfortable.
So it's not that. It sounds like what it is, is they're agreeing to, when they get pinged, saying, hey, you need to tone it down right now. That's when they need to either shift to on-site generation, backup, or find some virtual battery resource that they can use to pull power. Is that the right…