Northrup was explaining why data centers in utility forecasts often never show up. Along with permitting delays and speculative projects, she points to developers shopping the same project to several utilities at once.
…because of potential permitting delays, whether or not the need for compute looks the same if we're talking about a data center. Also, there's a lot of speculative. Of load where there's an element of how fast can you know we get speed to power this big topic that we're thinking about a lot.
Yeah, yeah.
And because the speed to power is a priority, sometimes there'll be double counting of a load because they're testing out one utility or another utility to see which they can get power in faster.
Yeah, this is worth spelling out a little bit because interconnection queues are so slow, because it's so difficult to get hooked up at all. Lots of large loads just sort of shop around and put themselves in line at a bunch of different utilities, just waiting to see when or if a utility will…
So it depends on where you are. In a vertically integrated utility model, where the utility recovers the capital that it spends under its regulatory framework, if they've made capital investments to support the slow growth and the load doesn't arrive, their other customers are on the hook to pay…
And we've seen this. I mean, this again is not theoretical too. Like we've seen this happen. We've seen utilities build in anticipation of loads and loads not show up, data centers not show up. I mean, is this something we've seen happen yet? Or is this just a theoretical worry?